Building begins

Thursday 29th May 2014

 

The second day on site has seen a lot of progress, with the delivery of more materials and the start of digging. Between us, we have shoveled over ten tonnes of gravel and earth onto a tractor to be transported to our site. The gravel will be used to in the foundations, with a layer of loose gravel and a layer of gravel bags providing structural support to the rest of the dome. The earth will be used to fill the bags and create the main structure of the dome while the turf removed from site will be incorporated into the roof system at a later date.  Some of the team have been digging all day to complete the trenches for foundations, digging around 600 mm into the ground. The drainage system has also been started and the frame for the door built so hopefully progress will continue at this pace for a few days!